phase 01: SCHEMATIC DESIGN
District Facility Program
Committee Meetings
Site Visits & Dialogue with M&O Staff
Educational Specifications
District Standards
FUNDING / AGENCY STRATEGY
OPSC
CDE
DSA
DTSC
Local Agencies
District Staff
PHASE 02: DESIGN DEVELOPMENT
Develop Detailed Ed. Specs and Program Documents
Review with District Representatives
Develop Design Schemes
Review with District Representatives
Continue Work on Selected Design Schemes
Review with District Representatives
Repeat Process until All Stakeholders are Satisfied
PHASE 03: CONSTRUCTION DOCUMENTS
Translate Design Documents to Technical Documents
Assemble most Competent Team
Include District Staff in Development of Documents
Little Things Matter (Outlets, Hose Bibs, Storage)
Compliance with District Standards
Preliminary Review with Agencies
Attention to Budget and Timeline
In-house Quality Review
Please give us a call to discuss your upcoming project.
Upland: (909) 985-6939 / Sacramento: (916) 231-0740
pHASE 04: bIDDING
Assist District in Determining Best Delivery Method
(CM, Open Bid, Design-Build, etc.)
Pre-Qualification of Bidders
Timely Response to Bidder’s Questions
Full Compliance with Public Contract Code
Analysis of Bid Figures
School Board Package for Bid Award
PHASE 05: CONSTRUCTION ADMINISTRATION
Pre-Construction Conference (District and Site Rules)
Timely Response to Contractor’s Questions
Eye on Budget and Schedule
Attention to Close-out Process
Timely Filing of Agency Documents
Successful Close-out of Project
PHASE 06: CLOSEOUT
Continue to Support District in Obtaining
Warranty Commitments from Contractor
Follow-up on any Agency Issues
Provide any Required User Manual from Ed.
Specs